All the San Antonio street work expected to end within the next year

If you live or work within the major metro area of San Antonio then you have probably run into traffic or closed streets because of these ongoing street projects around the Alamo City. A lot of these projects, if not done by TxDOT, are funded by the 2017-2022 multimillion-dollar bond, so the City of San Antonio tracks the projects on its website. Some projects are expected to continue into 2025. 

Cumulatively the $254.7 million has been spent on bond-funded street work The website says that there are 10 bond-funded street projects across multiple districts that are “on time” to finish within the next year. This includes projects that are expected to finish before the year is out in December.

Here are the projects expected to finish within the next year.

Erick Bryan swings a sledgehammer while working on a street project along Commerce and SW 19th streets in June 2022.

Kin Man Hui, San Antonio Express-News / Staff photographer

North St. Mary’s Street (East Mistletoe Avenue to West Josephine Street)

Council place: District 1

Status: On Time

Phase: Construction

Expected end date: August 2023

Note: This road work has been a point of contention for some businesses and residents along North St. Mary’s Street, whom are also at odds over proposed residential parking permits. The project has been delayed and dropped a subcontractor midway through the project. 

Aaron Peña, owner of Squeezebox, has been vocal on Twitter about the road work and says the street closures and narrowing of lanes will put people “out of business.”

District 1 Pedestrian Mobility & Streets

Council place: District 1

Status: On Time

Phase: Construction

Expected end date: September 2023

Note: Mobility and streets projects usually include construction of sidewalks and crosswalks.

Old Highway 90 Phase 1 (Old Highway 90 Area)

Council place: District 6

Status: On Time

Phase: Construction

Expected end date: December 2022

District 9 Pedestrian Mobility and Streets

Council place: District 9

Status: On Time

Phase: Construction

Expected end date: December 2022

District 7 Sidewalks

Council place: District 7

Status: On Time

Phase: Construction

Expected end date: December 2022

Note: This includes improvements to sidewalks on Wilson Boulevard (Club Drive to Babcock Road), west side of Fredericksburg Road (N. Zarzamora to Balcones Heights Boulevard), one side of Loma Linda Drive (Babcock Road to Williamsburg Place), west side of Lake Boulevard (Club Drive to West Woodlawn Avenue), and Benrus Boulevard. 

District 2 Pedestrian Mobility and Streets

Council place: District 2

Status: On Time

Phase: Construction

Expected end date: December 2022

District 3 Pedestrian Mobility & Streets

Council place: District 2

Status: On Time

Phase: Construction

Expected end date: December 2022

Fredericksburg Road (North Flores Street to West Woodlawn Avenue)

Council place: District 1

Status: On Time

Phase: Construction

Expected end date: February 2023

Camaron Street (West Houston Street to Fox Tech High School)

Council place: District 1

Status: On Time

Phase: Construction

Expected end date: January 2023

Commerce Street (St. Mary’s Street to Santa Rosa Street)

Council place: District 1

Status: On Time

Phase: Construction

Expected end date: January 2023